How to Write an Office Fit-Out RFP in India: Scope, Pricing Format and Evaluation (2026)

By Gurpreet Singh, Co-Founder9 min read

Short answer

A good office fit-out RFP gives every bidder the same brief, the same scope boundaries and the same pricing format, so the quotes you get back can be compared line by line. It should include the site details, a clear scope matrix, a specification level, a priced BOQ format, your commercial terms, the timeline and the scoring method. Do this well and the lowest credible quote becomes easy to spot.

Fit-out RFP in 10 sections

Give every bidder the same brief

  1. Company and project overview
  2. Site information
  3. Space programme
  4. Scope matrix
  5. Specification level
  6. Pricing format
  7. Programme
  8. Commercial terms
  9. Submission requirements
  10. Evaluation method
  1. Week 1RFI
  2. Week 2RFP issue
  3. Week 2Site visit
  4. Weeks 2–3Queries
  5. Week 4Bids due
  6. Weeks 5–6Award
The ten sections of an office fit-out RFP and an example six-week timeline.

Why RFP quality matters more this season

Office demand in India is holding up, and rents are rising. Figures reported on 12 October 2026 put leasing across eight major markets at about 66.7 million sq ft in the first nine months of the year, level with 2025. Annual rent growth in the third quarter ranged from 3% to 13%, with NCR at about 12%. Many companies signing leases now will move in during 2027, and most will try to finish their fit-out inside the rent-free period.

That leaves little time for a messy tender. When an RFP is vague, bidders fill the gaps with their own assumptions. One prices premium glass, another prices basic gypsum. One includes HVAC, another leaves it out. You then spend weeks normalising quotes that were never comparable. A clear RFP saves those weeks and protects the budget. Our guide on why contractors quote different prices for the same office explains where the gaps usually hide.

RFI, RFQ and RFP: which do you need?

  • RFI (Request for Information): A short questionnaire to build a shortlist. You ask about experience, team, financial strength and similar-sized projects.
  • RFQ (Request for Quotation): A price request against a completed design and BOQ. Use it when your design is already finished and you only need a contractor to build it.
  • RFP (Request for Proposal): A request for a full proposal covering approach, design, price, programme and team. This is the right format for design-and-build or turnkey projects, where bidders propose both the design and the build.

For most companies leasing a new office, a short RFI followed by an RFP to three to five shortlisted firms works well.

The ten sections of a fit-out RFP

#SectionWhat to include
1Company and project overviewWho you are, why you're moving, target move-in date, decision-makers
2Site informationAddress, floor(s), carpet and super area, shell condition (bare or warm shell), landlord fit-out manual, building drawings
3Space programmeHeadcount now and in 3–5 years, workstations, cabins, meeting rooms, collaboration, pantry, server room, special areas
4Scope matrixWho supplies what: landlord, contractor, your IT team, other vendors
5Specification levelQuality band, preferred brands or "or equivalent" lists, sustainability goals
6Pricing formatA common BOQ or price schedule, provisional sums, exclusions, GST shown separately
7ProgrammeLease dates, rent-free period, access date, working-hour restrictions
8Commercial termsPayment milestones, retention, liquidated damages, defects liability period, insurance, warranties
9Submission requirementsWhat bidders must submit, format, deadline, site visit date, query window
10Evaluation methodHow you will score technical and commercial bids

Section by section: the details that make quotes comparable

Space programme: give bidders real numbers

The space programme is the brief. If you are not sure what to put in it, start with our list of information to give your designer before the first layout.

Site information: share the landlord's documents

Attach the landlord's fit-out manual and as-built drawings, including floor plans, HVAC provisions, electrical load available, fire system details and structural limits. Bidders who cannot see these will either load their prices for risk or leave things out. Arrange one common site visit so every bidder sees the same conditions.

Scope matrix: the single most useful page

Many pricing gaps come from scope boundaries. A simple matrix removes them. List each item and mark who is responsible:

  • Civil works, partitions, false ceilings and flooring
  • HVAC, including any landlord-provided base system and the tenant-side distribution
  • Electrical, UPS, DG backup and raw power
  • Fire detection, sprinklers and approvals
  • Structured cabling, Wi-Fi, access control, CCTV and AV
  • Loose and system furniture, and pantry equipment
  • Signage, branding and artwork
  • Statutory approvals, landlord approvals and NOCs
  • Active IT equipment, such as switches, firewalls and laptops (often your IT team)

Specification level: name a quality band

"Premium finish" means different things to different bidders. Describe the quality band in concrete terms, such as ceiling type, glass thickness, workstation system, flooring and lighting controls, and list acceptable brands with an "or equivalent" option.

Rate bands help with budgeting. Officea Design & Build publishes a 2026 rate card (per sq ft, GST extra) that is a useful reference point:

TierDelhi NCR & ChandigarhBangalore, Mumbai, Pune, Hyderabad, Chennai, Goa
Basic₹1,800₹2,000
Medium₹2,200₹2,400
Good₹2,600₹2,900
High end₹4,500₹5,000

Telling bidders "we are budgeting at roughly the Medium band" keeps proposals within a realistic range and stops them from over- or under-designing.

Pricing format: one schedule for everyone

  • Provide a price schedule split by trade, including civil and interiors, HVAC, electrical, fire, ELV and IT, furniture, and preliminaries.
  • Ask for quantities and rates, not just lump sums, so you can see where prices differ.
  • Define provisional sums (allowances for items not yet designed) yourself, and give every bidder the same figure.
  • Ask for a separate list of exclusions and assumptions. This is often where the real price difference is hidden.
  • Show GST separately on every line.

Programme: anchor it to the lease

State the access date, rent-free period and target move-in. Mention any building restrictions, such as night-only noisy work, goods-lift slots or weekend access. Ask each bidder for a week-by-week programme showing design approval, long-lead items such as HVAC units, glass and furniture, and the commissioning period. For typical durations, see how long an office fit-out takes in India.

Commercial terms: decide them before you tender

Put your proposed payment milestones, retention, liquidated damages for delay, defects liability period, warranties and insurance requirements in the RFP. Then ask bidders to confirm acceptance or list deviations. Negotiating these after selecting a firm weakens your position and delays the start.

How to evaluate the proposals

Use a two-stage evaluation. Score the technical proposal first, then open the commercial bids of those that pass a minimum technical score. The weights below are only an example. Set your own before you issue the RFP and share them with bidders.

CriterionExample weightWhat to look for
Design response and test fit20%Meets the space programme, efficient planning, sensible growth allowance
Relevant experience15%Similar size and type of projects, verifiable references and site visits
MEP capability15%In-house or committed MEP design and execution, not an afterthought
Programme and methodology15%Realistic schedule, long-lead planning, site management plan
Team and accountability10%Named project manager, single point of contact, escalation route
Price (normalised)25%Price after adjusting for exclusions and scope gaps

"Normalised" is the important word. Before comparing prices, add back anything a bidder excluded that others included, using an agreed rate. The lowest headline number is often not the lowest real cost.

A realistic RFP timeline

  • Week 1: Issue the RFI and shortlist three to five firms.
  • Week 2: Issue the RFP, then hold a joint site visit.
  • Weeks 2–3: Query window. Share all answers with every bidder.
  • Week 4: Proposals due.
  • Week 5: Presentations, clarifications and technical scoring.
  • Week 6: Commercial normalisation, negotiation and award.

Six weeks is achievable for a typical office if decision-makers are available. Shortening the bid period below about two weeks usually leads to rushed, assumption-heavy proposals.

Common RFP mistakes

  • Sending only a floor plan and asking for "your best price"
  • No scope matrix, so HVAC, fire or furniture is left in no-man's land
  • Allowing each bidder to use its own BOQ format
  • Answering a query for one bidder without telling the others
  • Choosing on headline price before normalising exclusions
  • Leaving commercial terms to "discuss later"

Where a design-and-build partner fits

With a traditional route, you appoint a designer, finish the drawings and BOQ, then tender the build. With a design-and-build or turnkey RFP, each bidder proposes the design and the price together, and the winning firm takes single-point accountability for design, MEP, civil work and furniture through to handover. Officea Design & Build works on this model pan-India. Its published case studies include a 3,000 sq ft Gurgaon office delivered in 28 days and a 10,000 sq ft Noida office delivered in 43 days. Whichever route you choose, the same RFP discipline applies. For the trade-offs, read design and build vs traditional office fit-out and see our design and build service.

Frequently asked questions

What should an office fit-out RFP include?

It should include a company and project overview, site information and landlord documents, the space programme, a scope matrix, the specification level, a common pricing format, the programme, commercial terms, submission requirements and the evaluation method. Together these let every bidder price the same thing.

How many contractors should I invite to bid for an office interior project?

Three to five shortlisted firms is usually enough. Fewer limits competition, while more creates evaluation work and discourages serious bidders, who know their odds are low. Use a short RFI first to filter for relevant experience and capacity.

How long should bidders get to respond to a fit-out RFP?

About two to three weeks, including a site visit and a query window, is reasonable for most offices. Larger or more complex projects may need longer. Very short deadlines tend to produce proposals full of assumptions and exclusions.

Why are fit-out quotes for the same office so different?

The usual reasons are different scope assumptions, different specifications and different exclusions, rather than very different margins. A common scope matrix, a defined quality band and a single pricing format remove most of this variation.

Should I use a design-and-build RFP or tender a completed design?

Design-and-build suits companies that want speed and one accountable party, and that can describe their needs clearly. Tendering a completed design suits companies that want to fix the design in detail before pricing, and that have time for a longer, two-stage process.

What does an office fit-out cost per sq ft in 2026?

Officea's published 2026 rates in Delhi NCR are ₹1,800 (Basic), ₹2,200 (Medium), ₹2,600 (Good) and ₹4,500 (High end) per sq ft, GST extra. Bangalore, Mumbai, Pune, Hyderabad, Chennai and Goa run about 10% higher. Actual costs depend on the building, scope and specification.

Preparing an RFP for a new office? Officea Design & Build offers a complimentary site visit and a layout and budget estimate you can use to set a realistic budget band before you tender. Request yours here.

Sources

Planning an office project?

Officea Design & Build plans, designs and builds corporate offices across India under one contract. See our work or the full list of design and build services, or tell us your city, approximate area and target move-in date below and we'll prepare a costed proposal.

Estimate your fit-out cost

Officea's own 2026 rates by tier. Not a quote — send us your details below for an exact number.

Office fit-out cost per sq ft, 2026 rate card (GST extra). Last updated 11 October 2026.
TierDelhi, Gurgaon, Noida, ChandigarhBangalore, Mumbai, Pune, Hyderabad, Chennai, Goa
Basic₹1,800₹2,000
Medium₹2,200₹2,400
Good₹2,600₹2,900
High end₹4,500₹5,000

Bangalore, Mumbai, Pune, Hyderabad, Chennai and Goa run about 10% above Delhi NCR, rounded to the nearest ₹100. Rates cover civil, MEP, flooring, ceiling and standard finishes. Furniture is included in every Officea quote. See every city and tier side by side in the India office fit-out cost index. Plan workstations, cabins and meeting rooms in the office layout planner. See the city pages for Pune, Hyderabad, Chennai, Chandigarh and Goa.

Fit-out tier
₹1,10,00,000
≈ $115,789 total · ₹2,200 / sq ft (≈ $23.16)

Officea's own 2026 indicative rates per sq ft, covering civil, MEP, furniture and finishes at the stated tier. For early budgeting only — exact pricing is confirmed in a written proposal.

Want the exact number for your office?

Complimentary download

The same cost benchmarks and planning checklist as a PDF you can keep and share with your team.

2026 Office Fit-Out Planning & Cost Guide

  • 2026 city-by-city cost benchmarks
  • What actually moves your cost per square foot
  • A before-you-sign, during-construction and handover checklist