How to Set an Office Fit-Out Budget Before You Call Contractors

By Gurpreet Singh, Co-Founder9 min read

Quick answer

Set the budget from your own numbers before any contractor quotes: headcount and growth give the carpet area, area multiplied by a rate card tier gives the fit-out figure, and then you add the items outside the fit-out contract, GST and a contingency. With Officea’s 2026 rate card for Delhi NCR (₹1,800 to ₹4,500 per sq ft, furniture included, GST extra), a 60-seat office of about 5,400 sq ft at Medium comes to about ₹1.19 crore before GST.

Open office with an oval suspended ceiling feature with LED cove, wood-look vinyl flooring, glass partition on the left and workstations along the windows
A completed office from Officea’s portfolio.

How do you set an office fit-out budget before calling contractors? Work out the area you need, price it against a published rate, then add what sits outside the fit-out. This guide walks through each step with worked figures, so the CFO, the admin head and the board agree a number before the first quote arrives, and every quote is judged against it.

Why set the budget before contractors quote?

If the first number you see is a contractor’s, that number becomes the budget. You end up judging quotes against each other, not against what the office should cost, and the cheapest bid looks like a saving even when it covers less work.

A budget you set yourself does three things. It tells the board early whether the move is affordable. It lets you brief bidders with a clear specification level, so they price the same office. And it gives you a yardstick: a quote far above or below it is a prompt to ask questions, not a reason to sign. Our office fit-out checklist for CFOs covers the approvals that follow.

How much area are you budgeting for?

Fit-out is priced per square foot, so area is the biggest lever in the budget. Start with people, not a floor you have seen.

  1. Count seats today. Desks, cabins and any shared or hot desks, by team.
  2. Add growth. Plan for the headcount you expect over the lease, or at least the first few years of it.
  3. Choose a space standard. Measured on carpet area and including a share of cabins, meeting rooms, pantry, reception and circulation, space per seat ranges from about 50 sq ft (dense) to 120 sq ft (generous). Most corporate offices land at 80 to 100 sq ft.
  4. Multiply. 60 seats at 90 sq ft is about 5,400 sq ft of carpet area.

Budget on carpet area, the space you actually fit out, not the chargeable or super area on the lease. For a fuller table by team size, see how many people fit in 1,000 to 10,000 sq ft.

Which rate tier fits your office?

Officea’s 2026 rate card for Delhi, Gurgaon and Noida has four tiers. Furniture is included and GST is extra. Bangalore, Mumbai, Pune, Hyderabad, Chennai and Goa run about 10% higher.

TierRate (Delhi NCR)Rate (other metros, about)
Basic₹1,800 per sq ft₹1,980 per sq ft
Medium₹2,200 per sq ft₹2,420 per sq ft
Good₹2,600 per sq ft₹2,860 per sq ft
High end₹4,500 per sq ft₹4,950 per sq ft

You do not have to pick one tier for the whole floor. Reception, the boardroom and client meeting rooms are what visitors see; open workspace and back-of-house areas are used hard but seen less. A blended rate, with a higher tier for the front-of-house zones and a lower one elsewhere, often gives a better office for the same money. What each tier means in finishes is explained in the office fit-out cost guide for India in 2026.

What does an office fit-out cost by headcount?

The table applies the Delhi NCR rate card to common team sizes at 90 sq ft a seat. Figures are before GST.

Seats (carpet area)BasicMediumGoodHigh end
30 (2,700 sq ft)₹48.6 lakh₹59.4 lakh₹70.2 lakh₹1.22 crore
60 (5,400 sq ft)₹97.2 lakh₹1.19 crore₹1.40 crore₹2.43 crore
100 (9,000 sq ft)₹1.62 crore₹1.98 crore₹2.34 crore₹4.05 crore
200 (18,000 sq ft)₹3.24 crore₹3.96 crore₹4.68 crore₹8.10 crore

Change the space standard and the whole row moves: at 80 sq ft a seat, 100 people need about 8,000 sq ft instead of 9,000. Cost per seat is a useful second view for the board; cost per seat vs cost per sq ft explains when to use each. The calculator further down this page runs the same arithmetic for your own area and city.

What sits outside the fit-out budget?

A fit-out rate covers building the office. Some costs belong to the move instead, and they are the usual reason a budget is short. Give each its own line:

  • IT and cabling: structured cabling, network equipment, Wi-Fi and the server room.
  • AV: screens, cameras, microphones and booking panels for meeting rooms.
  • Security: access control, CCTV and visitor management.
  • Signage and branding: reception logo, wayfinding and glass manifestation.
  • Blinds, plants and accessories.
  • Landlord and building charges: fit-out deposits, approval fees, after-hours working charges and any services the building asks you to upgrade.
  • Moving: packing, transport, IT migration and disposal of old furniture.
  • Overlap rent: the old office while the new one is built, less any rent-free period. See fit-out timelines and rent-free periods.

Get a figure for each from the relevant vendor or the building’s fit-out manual rather than guessing. Our guide to hidden costs in an office fit-out shows where each of these tends to hide in a quote.

How should you handle GST and contingency?

GST. Officea’s rates, like many fit-out quotes in India, are stated GST extra. Put GST on its own line so the board sees the cash figure, and compare quotes only after GST is added to each on the same basis. Whether your company can claim input tax credit on the fit-out depends on how the work is treated in your accounts, so confirm the rate and your credit position with your chartered accountant.

Contingency. Hold a separate line for decisions that change after the contract and for what the site reveals once work starts. Keep it out of the contractor’s scope and do not spend it on upgrades. How much to hold depends on risk: a new fit-out in a warm shell with headcount, cabins and finishes frozen needs little; refurbishing an older floor, working around an occupied office or starting from a bare shell needs more. The difference between shells is covered in bare shell vs warm shell.

Worked example: a 60-seat office in Delhi NCR

A company of 60 people plans a new office in Gurgaon. The arithmetic below uses only the published rate card; the other lines are left for the company’s own vendor figures.

LineBasisAmount (before GST)
Carpet area60 seats × 90 sq ft5,400 sq ft
Front of house (reception, boardroom, client meeting room)600 sq ft × ₹2,600 (Good)₹15.6 lakh
Workspace and back of house4,800 sq ft × ₹2,200 (Medium)₹1.06 crore
Fit-out totalBlended about ₹2,244 per sq ft, furniture included₹1.21 crore
IT, AV, security, signage, moving, landlord charges, overlap rentVendor and building figuresAdd each line
ContingencySeparate line, sized to riskAdd
GSTOn each line, at the applicable rateAdd

The fit-out alone works out to about ₹2 lakh a seat. The same office in Bangalore would run about 10% higher, around ₹1.33 crore. If the board’s ceiling is lower, the levers are area first (85 sq ft a seat saves about 300 sq ft) and the tier mix second, before any cut to services or safety.

How do you use the budget with contractors?

  1. Brief to the budget. Tell bidders the area, the tier for each zone and the scope, including what is excluded. Do not tell them the figure; tell them the specification it buys.
  2. Ask for the same format. A BOQ with named brands, matching quantities and the same provisional sums in every quote.
  3. Check the programme. A realistic timeline protects the overlap rent line; the fit-out timeline calculator gives a range for your size.
  4. Judge against your number. A quote well below the tier it claims needs a line-by-line check; see is the lowest quote really cheaper?

Send up to three quotes for a complimentary quote comparison and we will line them up against each other and the rate card. Officea designs and builds offices under one contract from studios in Delhi (Nehru Place), Gurgaon (DLF Grand Mall), Noida (Sector 3) and Bangalore (Residency Road). For answers to other common office problems, see office problems and solutions.

Frequently asked questions

How do I set an office fit-out budget?

Fix your headcount and growth, convert it to carpet area at 50 to 120 sq ft a seat (80 to 100 is typical), multiply the area by a rate card tier, add the items that sit outside the fit-out contract, then add GST and a contingency. Do this before you invite quotes so every bidder prices against the same number.

What rate per sq ft should I use for an office fit-out budget?

Officea's 2026 rate card for Delhi NCR is ₹1,800 per sq ft for Basic, ₹2,200 for Medium, ₹2,600 for Good and ₹4,500 for High end, with furniture included and GST extra. Bangalore, Mumbai, Pune, Hyderabad, Chennai and Goa run about 10% higher.

What is not included in an office fit-out budget?

Items that belong to the move rather than the build: IT and cabling, AV, security systems, signage, blinds and plants, moving costs, landlord charges and overlap rent on the old office. Add a line for each, plus GST, to reach the full budget.

How much contingency should an office fit-out budget have?

Hold a separate contingency line for decisions that change after the contract and for site surprises, and do not spend it on upgrades. Keep it small for a new fit-out in a warm shell with frozen decisions, and larger for refurbishing an occupied or older floor.

Should I budget per seat or per sq ft?

Use both. Cost per sq ft is how contractors price and how you compare quotes; cost per seat is how the board judges value. For example, 5,400 sq ft at a blended ₹2,244 per sq ft is about ₹1.21 crore, or about ₹2 lakh for each of 60 seats, before GST.

Can Officea check my budget before I go to contractors?

Yes. Share your headcount, city and floor details and we will prepare a costed proposal against the rate card. If you already have quotes, send up to three for a complimentary item-by-item comparison.

Planning an office project?

Officea Design & Build plans, designs and builds corporate offices across India under one contract. See our work or the full list of design and build services, or tell us your city, approximate area and target move-in date below and we'll prepare a costed proposal.

Estimate your fit-out cost

Officea's own 2026 rates by tier. Not a quote — send us your details below for an exact number.

Office fit-out cost per sq ft, 2026 rate card (GST extra). Last updated 11 October 2026.
TierDelhi, Gurgaon, Noida, ChandigarhBangalore, Mumbai, Pune, Hyderabad, Chennai, Goa
Basic₹1,800₹2,000
Medium₹2,200₹2,400
Good₹2,600₹2,900
High end₹4,500₹5,000

Bangalore, Mumbai, Pune, Hyderabad, Chennai and Goa run about 10% above Delhi NCR, rounded to the nearest ₹100. Rates cover civil, MEP, flooring, ceiling and standard finishes. Furniture is included in every Officea quote. See every city and tier side by side in the India office fit-out cost index. Plan workstations, cabins and meeting rooms in the office layout planner. See the city pages for Pune, Hyderabad, Chennai, Chandigarh and Goa.

Fit-out tier
₹1,10,00,000
≈ $115,789 total · ₹2,200 / sq ft (≈ $23.16)

Officea's own 2026 indicative rates per sq ft, covering civil, MEP, furniture and finishes at the stated tier. For early budgeting only — exact pricing is confirmed in a written proposal.

Want the exact number for your office?

Complimentary download

The same cost benchmarks and planning checklist as a PDF you can keep and share with your team.

2026 Office Fit-Out Planning & Cost Guide

  • 2026 city-by-city cost benchmarks
  • What actually moves your cost per square foot
  • A before-you-sign, during-construction and handover checklist