Officea Design & Build

Home / Problems and solutions / Fit-out timeline calculator

Office fit-out timeline calculator

How long will your office fit-out take? Enter the size of the office and a few facts about the building and scope. The calculator gives a range in weeks from brief to handover, compares one design and build team with separate designers and contractors, and checks the result against your rent-free period. It uses the same ranges as our fit-out timeline guide.

Also true for this project

How long an office fit-out takes, by size

These are typical ranges from brief to handover when design, approvals, ordering and site work overlap under one team. The calculator starts from this table and adjusts it for your building and scope.

Office sizeTypical range, brief to handover
Up to 5,000 sq ft4–8 weeks
5,000–10,000 sq ft6–12 weeks
10,000–25,000 sq ft10–18 weeks
25,000–50,000 sq ft14–24 weeks
Above 50,000 sq ft20–36 weeks or more

Phase by phase durations and rent-free planning: office fit-out timeline in India.

What the calculator adjusts for

Floor condition

A bare shell needs flooring, ceilings, air conditioning and power distribution built from scratch. Reusing an existing fit-out shortens the site work.

Services work

New air conditioning, fire system changes and facade work need more design, approvals and testing. See VRF vs chilled water and fire safety requirements.

SEZ buildings

Customs and development commissioner steps add time to approvals and to bringing materials in. See SEZ vs non-SEZ fit-out.

Imported items

Imported furniture, lighting or finishes often have the longest lead times on the project and need ordering early.

Occupied offices

Working around staff means phased zones and night or weekend work. See how to refresh an office without stopping work.

An approved layout

If the layout is already agreed, design starts from the detailed drawings. Check it first with our floor plan approval checklist.

Officea's published project timelines

Actual durations from our four published case studies, design and build under one contract.

ProjectDurationIn weeks
3,000 sq ft, Gurgaon28 daysAbout 4 weeks
10,000 sq ft, Noida43 daysAbout 6 weeks
28,000 sq ft, Bangalore105 days15 weeks
42,000 sq ft, Udyog Vihar, Gurgaon105 days15 weeks

More on what made them fast: how long does an office fit-out take in India.

Questions about fit-out timelines

How long does an office fit-out take in India?

Typically 4 to 8 weeks for 2,000 to 5,000 sq ft, 6 to 12 weeks for 5,000 to 10,000 sq ft, 10 to 18 weeks for 10,000 to 25,000 sq ft, 14 to 24 weeks for 25,000 to 50,000 sq ft, and 20 to 36 weeks or more above that, brief to handover, with design and site work overlapping.

Why is the sequential estimate so much longer?

When the designer, the landlord approvals and the contractor work one after another, each stage waits for the last to finish. Under one design and build team, approvals, ordering and early site work start while the design is being completed.

Is the result a delivery commitment?

No. It is an indicative planning range. A programme for your office depends on the actual floor, the building's approval process and the final design. Send us the floor plan for one based on your site.

What makes a fit-out take longer?

A bare shell floor, new air conditioning or fire system changes, SEZ procedures, imported furniture or finishes, working around staff in an occupied office, and design changes after site work starts.

How long a rent-free period should we ask for?

At least the upper end of the range for your office, with design starting at or before lease signing. If the calculator shows your rent-free period is shorter, negotiate a longer fit-out period before you sign.

Have quotes with different timelines? Send them for a complimentary comparison. More answers on the problems and solutions page.