Office Relocation Checklist: The Timeline and the Total Cost of Moving

By Gurpreet Singh, Co-Founder10 min read

Quick answer

Start planning an office relocation 12 to 18 months before your lease ends, and work backwards from the date you must be out of the old office. The total cost of moving is much more than the fit-out: add the new security deposit, brokerage, the reinstatement of the old office, parallel rent while both offices are held, the IT and furniture move, and lost working time. In Delhi NCR, Officea’s published fit-out rates run from ₹1,800 per sq ft (Basic) to ₹4,500 per sq ft (High end), GST extra and furniture included, about 10% higher in Bangalore, Mumbai, Pune, Hyderabad, Chennai and Goa. Put every bucket in one budget before you sign the new lease.

Newly fitted open-plan office on moving day, with white workstations, grey chairs, a glass meeting room and a few stacked moving cartons by the entrance
Concept render: a new office on moving day. Illustration, not a completed project.

The new office looks right, the rent is agreed, and the board wants a move date. Then the real bill starts to arrive: a deposit on the new floor, brokerage, the fit-out, a letter from the old landlord about reinstatement, and two months of rent on two offices. Most relocation budgets in India go wrong because they count the fit-out and forget the rest. This guide is for CEOs, CFOs and admin heads: a timeline that works backwards from your move date, every cost bucket you need to budget, and a checklist you can hand to your team.

When should you start planning an office relocation?

Start 12 to 18 months before your current lease ends, or before the date your business needs the new space. That sounds early, but the time goes quickly:

  • Your notice date comes first. Most leases require written notice months before the end date. Miss it and you may be locked into a renewal or holding-over terms you did not choose.
  • Finding and negotiating the right floor takes time. Shortlisting buildings, test-fitting layouts, agreeing the term sheet and the lease can take several months on their own.
  • The fit-out itself usually takes 2 to 4 months from design start to handover for most offices, and longer for very large floors. The finish level and on-time stage payments decide where you land in that range; delayed payments delay handover.
  • The old office has to be handed back, often to bare shell, before the lease ends.

If you are not yet sure that moving is right, compare it properly first. Our guide to renewing or relocating your office sets out the decision, and repair, refresh or relocate helps you check whether the current office can be fixed instead.

What does a relocation timeline look like, working backwards?

Fix the date you must be out of the old office, then plan backwards. The timings below are typical for a mid-sized office; your lease and the size of the new floor will change them. The office move planner works out these dates for your own lease end and floor size, and the fit-out timeline calculator estimates the build stage.

When (before lease end)What happensWho leads
12 to 18 monthsDecide renew or relocate. Agree headcount, growth and hybrid-work assumptions. Set the total budget, not just the fit-out budget.CEO, CFO
9 to 12 monthsShortlist buildings. Get test-fit layouts for the top two or three floors so you compare usable seats, not just rent per sq ft.Admin head, broker, design and build firm
7 to 9 monthsNegotiate and sign the term sheet and lease: rent, rent-free fit-out period, deposit, handover condition, reinstatement terms.CFO, legal
By the notice date in your leaseServe written notice on the current landlord. Ask in writing which handback condition they want.Admin head, legal
5 to 7 monthsDesign, cost plan and approvals for the new office: layout, MEP, fire drawings, building permits.Design and build firm
2 to 5 monthsFit-out on site. Order IT, AV and network links early; telecom and ISP lead times can be long.Design and build firm, IT head
4 to 8 weeksSnagging, handover documents, IT installation and testing, moving company booked, staff briefed.Admin head, IT head
Move weekendPack, move, set up desks and IT, test, open on Monday.Admin head, movers, IT
Final weeks of the leaseStrip-out and reinstatement of the old office, joint inspection, keys returned, handback signed.Admin head, contractor

The weeks between handover of the new office and handback of the old one are the expensive part: you pay rent on both. Our guide to fit-out timelines and rent-free periods explains how to negotiate enough rent-free time to cover the build.

What is the total cost of moving an office?

The total cost of an office relocation is the sum of seven buckets. Only the first is the fit-out. Put all seven in one sheet before you sign anything.

Cost bucketWhat it coversHow to estimate it
1. Fit-out of the new officeDesign, civil and interiors, MEP, furniture, project managementCarpet area × the rate for your finish level, plus GST. See the next section.
2. Security depositRefundable deposit on the new lease, usually expressed as months of rentNumber of months in your term sheet × monthly rent. It is cash out of the business even though it comes back later.
3. BrokerageFee to the leasing broker, if you use oneAs agreed in writing with the broker before you start viewing; often linked to months of rent.
4. Parallel rentRent and maintenance on the old office while the new one is being built or settledOverlap months × (old rent + maintenance), minus any rent-free period on the new lease.
5. Reinstatement of the old officeRemoving your fit-out and making good, to the condition in the old leasePriced item by item against the lease requirement. There is no reliable per sq ft figure.
6. IT, AV and the physical moveNetwork links, cabling, server or comms room, AV, movers, packing, insuranceQuotes from your IT partner and two or three moving companies.
7. Downtime and changeLost working hours, overtime, temporary space, new stationery and signage, staff communicationHours lost × team size, plus a small allowance for the rest.

Two of these, the deposit and the parallel rent, often surprise CFOs most, because they are large and arrive before the business sees any benefit from the new space. Reinstatement is the one most often forgotten altogether; our guide to lease-end reinstatement explains what landlords ask for and how to plan it.

How much will the new fit-out cost?

For most moves, the fit-out is the largest single bucket. Officea’s published rate card for Delhi NCR is per sq ft of carpet area, GST extra, with furniture included:

Finish levelDelhi NCR (per sq ft)Example: 5,000 sq ft
Basic₹1,800₹90 lakh + GST
Medium₹2,200₹1.10 crore + GST
Good₹2,600₹1.30 crore + GST
High end₹4,500₹2.25 crore + GST

In Bangalore, Mumbai, Pune, Hyderabad, Chennai and Goa, rates are about 10% higher. The handover condition of the new floor matters too: a warm shell floor with the landlord’s air conditioning already in place needs less work than a bare shell. Our office fit-out cost guide for India breaks the rates down by city and scope, and the calculator further down this page gives a quick estimate for your area.

Before you lock the budget, check how much space you actually need. Moving is the best moment to right-size, and our guide to how much office space you need shows how to work it out from headcount and the way your teams work.

Which moving costs do budgets usually miss?

  • Reinstatement of the old office. Often left out of the relocation budget entirely, and it has to be finished before the lease ends.
  • Overlap longer than planned. If the new office is late, the old rent keeps running. Build a few weeks of buffer into the parallel rent line.
  • Network and telecom lead times. If the internet links are not live on moving day, the office cannot work. Order them as soon as the lease is signed.
  • Building charges. Fit-out deposits, permits, after-hours working charges and goods-lift bookings at both buildings.
  • Furniture you cannot reuse. Old desks rarely suit a new layout. Decide early what moves and what goes, and budget for disposal.
  • Things outside the fit-out quote. Compare quotes line by line so items like AV, access control or signage are not missing. Our quote comparison tool and the guide to hidden costs in office fit-outs help you spot gaps.
Open office at handover stage with new workstations, chairs still in plastic wrap, a wet-and-dry vacuum cleaner and extension cables on the carpet
Work in progress on an Officea fit-out.

What should be on your office relocation checklist?

Use this as a working list for your team. Each line has an owner and a date in your plan.

Decision and lease

  • Headcount today and in three years, and how many people will be in on a typical day
  • Total relocation budget covering all seven cost buckets
  • Test-fit layouts for shortlisted floors, so you compare usable seats
  • Term sheet: rent, escalation, rent-free fit-out period, deposit, lock-in, handover condition, reinstatement at exit
  • Notice to the current landlord served by the date in the lease, with a written request for their handback condition

Design and fit-out

  • Brief: seats, cabins, meeting rooms, pantry, server or comms room, storage, growth space
  • Design, cost plan and programme agreed before work starts
  • Landlord and building approvals, fire drawings and work permits in place
  • Stage payment schedule agreed, and paid on time to protect the handover date
  • Snagging inspection, as-built drawings, warranties and manuals at handover

IT, people and the move

  • Internet links, phone lines and network ordered early; Wi-Fi and printers tested before moving day
  • Moving company booked, with insurance and a packing plan by team
  • Seating plan, access cards and parking shared with staff before the move
  • Address change: GST registration, bank, clients, suppliers, website, Google Business Profile and letterheads
  • Day-one help desk for small fixes in the first week

Leaving the old office

  • Inventory of what moves, what is sold or donated and what is scrapped
  • Reinstatement scope priced and booked for the weeks after the move
  • Joint inspection with the landlord, keys and access cards returned, handback signed
  • Security deposit refund followed up, with any deductions itemised

Once the new office is built, our office handover checklist lists what you should receive from the contractor before the last payment.

How do you keep downtime to a weekend?

Most offices can move over a single weekend if the new space is finished, tested and snag-free before the move starts. The usual causes of a longer disruption are a late handover, network links that are not live, and furniture that arrives after the people. To avoid them:

  1. Get the new office handed over two to four weeks before moving day, so snags are closed and IT is installed in an empty, finished space.
  2. Test everything before the move: internet failover, Wi-Fi coverage, video-call rooms, printers, access control and air conditioning at full occupancy hours.
  3. Move by team, with labelled crates and a floor plan showing each person’s desk.
  4. Keep the old office running until the move is complete, then start reinstatement.

Officea plans, designs and builds offices from studios in Delhi (Nehru Place), Gurgaon (DLF Grand Mall), Noida (Sector 3) and Bangalore (Residency Road). If you are still looking for space, you can browse office space on officesonrent.com. If you have a floor in mind, send us the plan for a complimentary floor plan audit and we will show how many seats it fits and what the fit-out will cost. More answers to common office questions are on our office problems and solutions page.

Frequently asked questions

How early should we start planning an office relocation in India?

Start 12 to 18 months before your lease ends or before you need the new space. You need time to serve notice on time, find and negotiate the new floor, design and build the fit-out, which usually takes 2 to 4 months for most offices, and hand back the old office before the lease ends.

What is the total cost of moving an office?

Add seven buckets: the fit-out of the new office, the new security deposit, brokerage, parallel rent while both offices are held, reinstatement of the old office, IT and the physical move, and lost working time. The fit-out is usually the largest, but the deposit and parallel rent are often the biggest surprises.

How much does an office fit-out cost per sq ft when relocating?

Officea’s published Delhi NCR rates are ₹1,800 per sq ft for Basic, ₹2,200 for Medium, ₹2,600 for Good and ₹4,500 for High end, GST extra and furniture included. Rates are about 10% higher in Bangalore, Mumbai, Pune, Hyderabad, Chennai and Goa.

Do we have to pay rent on both offices during the move?

Usually yes, for a period. The old lease runs until its end date and the new lease starts on its own date. A rent-free fit-out period on the new lease reduces the overlap, so negotiate it in the term sheet and plan the move so that reinstatement of the old office fits inside the remaining weeks.

Can an office move be done without stopping work?

Most offices can move over a single weekend if the new office is handed over, snagged and tested two to four weeks before moving day, internet links are live, and the move is planned team by team with a seating plan.

Planning an office project?

Officea Design & Build plans, designs and builds corporate offices across India under one contract. See our work or the full list of design and build services, or tell us your city, approximate area and target move-in date below and we'll prepare a costed proposal.

Estimate your fit-out cost

Officea's own 2026 rates by tier. Not a quote — send us your details below for an exact number.

Office fit-out cost per sq ft, 2026 rate card (GST extra). Last updated 11 October 2026.
TierDelhi, Gurgaon, Noida, ChandigarhBangalore, Mumbai, Pune, Hyderabad, Chennai, Goa
Basic₹1,800₹2,000
Medium₹2,200₹2,400
Good₹2,600₹2,900
High end₹4,500₹5,000

Bangalore, Mumbai, Pune, Hyderabad, Chennai and Goa run about 10% above Delhi NCR, rounded to the nearest ₹100. Rates cover civil, MEP, flooring, ceiling and standard finishes. Furniture is included in every Officea quote. See every city and tier side by side in the India office fit-out cost index. Plan workstations, cabins and meeting rooms in the office layout planner. See the city pages for Pune, Hyderabad, Chennai, Chandigarh and Goa.

Fit-out tier
₹1,10,00,000
≈ $115,789 total · ₹2,200 / sq ft (≈ $23.16)

Officea's own 2026 indicative rates per sq ft, covering civil, MEP, furniture and finishes at the stated tier. For early budgeting only — exact pricing is confirmed in a written proposal.

Want the exact number for your office?

Complimentary download

The same cost benchmarks and planning checklist as a PDF you can keep and share with your team.

2026 Office Fit-Out Planning & Cost Guide

  • 2026 city-by-city cost benchmarks
  • What actually moves your cost per square foot
  • A before-you-sign, during-construction and handover checklist