Key points
- Lump sum: one price for a defined scope; the contractor carries the quantity risk.
- Item rate: fixed rates per BOQ item, paid on measured quantities; the quantity risk stays with you.
- A lump sum only prevents extras when drawings and specifications are complete at tender.
- For refurbishments, price the visible work as a lump sum and hidden work on item rates.
What is the difference between a lump-sum and an item-rate fit-out contract?
In a lump-sum contract you agree one price for a defined scope and set of drawings, and the contractor carries the risk on quantities. In an item-rate contract you agree a rate for each BOQ item and pay for the quantities actually measured, so the quantity risk stays with you.
Both use a bill of quantities. In a lump sum, the BOQ is a breakdown of the agreed price and the basis for pricing changes. In an item-rate contract, the BOQ is the payment mechanism: quantities are measured on site and paid at the agreed rates. In both, a change in scope is a variation. If BOQs are new to you, start with what a BOQ is in an office fit-out.
Lump sum vs item rate compared
| Lump sum | Item rate (BOQ) | |
|---|---|---|
| Price certainty at signing | High, for the defined scope | Rates fixed; total moves with measured quantities |
| Who carries quantity risk | The contractor | You |
| What you need before tender | Complete drawings and specifications | A BOQ with estimated quantities; drawings can still be developing |
| How changes are priced | As variations, from BOQ rates where possible | Quantity changes at BOQ rates; new items need new rates |
| How bills are checked | Against milestones or percentage complete | Joint measurement of work done |
| Admin effort for you | Lower | Higher: measurement and checking of every bill |
Which one fits your project?
| If this is you | Better choice | Why |
|---|---|---|
| Design is complete and the scope will not change | Lump sum | You get a firm total and the contractor carries quantity risk |
| You must start before drawings are final | Item rate | Work can begin on agreed rates while design finishes |
| Refurbishing an occupied office | Lump sum plus item-rate schedule for hidden work | Price what you can see; agree rates for what you cannot |
| You want one firm responsible for design and price | Design and build with a fixed price after BOQ approval | Design and cost are developed by the same team |
| No one on your side can check measurements | Lump sum | Item-rate bills need measuring and checking |
Which contract leads to fewer extras?
A lump sum leads to fewer extras only when the drawings and specifications are complete at tender. Signed on incomplete drawings, it simply moves the extras into variation claims.
Extras on fit-outs come from a short list of places: items missing from the BOQ, provisional sums and allowances, loose specifications such as “or equivalent”, site conditions found after work starts, and changes the client asks for. A lump sum removes only the quantity risk. The rest has to be closed by complete drawings and a clear specification before you sign.
Under design and build, the same team develops the design and the BOQ, so the price can be fixed once you approve both. At Officea you get a costed BOQ before work starts. See design and build vs traditional fit-out.
How do you compare lump-sum quotes fairly?
Ask every bidder to price the same drawings and BOQ, to list exclusions and provisional sums separately, and to state the area basis. Compare the totals only after adding the exclusions back in.
Two lump sums for the same office can differ widely because one excludes items the other includes. Put the quotes side by side line by line, add a realistic figure for each exclusion (see hidden costs in an office fit-out for the usual ones), and check that both are priced on carpet area. Our fit-out RFP guide gives a format that makes quotes comparable from the start. Before you pick the lowest total, read is the lowest office fit-out quote really cheaper?
What should a fit-out contract say about variations?
That no variation is carried out without a written instruction, that it is priced from the contract BOQ rates where an equivalent item exists, and that the cost and time impact are agreed before the work starts.
Add a rule for new items with no BOQ rate (for example, rate analysis from material and labour costs with an agreed margin), a running variation register shared every week, and a single person on your side with authority to approve. These three lines prevent most disputes at final account.
Can you have a lump sum on an occupied-office refurbishment?
Yes, for the work you can see and measure. Keep a short item-rate schedule for hidden work such as concealed services or damaged slabs, so it is paid at agreed rates if it turns up instead of being negotiated mid-job.
Refurbishments carry more unknowns than a new floor, because walls, ceilings and services hide conditions nobody can price in advance. A survey before tender, opening up a few sample areas, shrinks the unknown part. The renovation vs refresh guide explains which kinds of work open up the building and which do not.
See every Officea comparison, each with a short answer, on the office fit-out comparisons page.
Next step. Comparing a lump-sum quote with an item-rate one? send them to us for a complimentary line-by-line comparison before you sign.