Office interior fit-out in Bangalore costs ₹2,000 per sq ft (Basic), ₹2,400 (Medium), ₹2,900 (Good) and ₹5,000 (High end) in 2026, GST extra, furniture included. A 2,000 sq ft office comes to about ₹40 lakh at Basic, or ₹1.6 to ₹2.0 lakh per seat. Bangalore rates run about 10% above Delhi NCR, and they are published, not quote-only. This guide gives worked budgets, cost per seat, the cost picture in each office market and what the rate leaves out.
Key takeaways
- ₹2,000 to ₹5,000 per sq ft in Bangalore in 2026 for a complete turnkey fit-out: Basic ₹2,000, Medium ₹2,400, Good ₹2,900, High end ₹5,000. GST extra, furniture included.
- A 5,000 sq ft office costs ₹1 crore to ₹2.5 crore; 10,000 sq ft costs ₹2 crore to ₹5 crore, depending on tier.
- ₹1.6 to ₹5.0 lakh per seat, planned at 80 to 100 sq ft per seat.
- MEP is the biggest cost head, about 28% of a Medium-tier budget, ahead of civil work (22%) and furniture (20%).
- 6 to 16 weeks from design freeze to handover for most offices; our 28,000 sq ft Bangalore office took 105 days.
- Not in the rate: GST, landlord deposits and drawing fees, after-hours building charges, and finishes above your tier.
Our Bangalore studio: AWFIS, Sabari Complex, 24 Field Marshal Cariappa Rd, Residency Road, Bengaluru 560025 (open in Google Maps). Call +91 98711 11446 to visit, or see our 28,000 sq ft Bangalore office with stone cladding and curved glass.
Bangalore office interior rates for 2026
These are Officea Design & Build's published 2026 rates per sq ft for a complete turnkey fit-out in Bangalore: civil and interiors, MEP, workstations, loose furniture and finishes. GST is extra.
| Tier | Rate (₹ per sq ft, GST extra) | What you get |
|---|---|---|
| Basic | ₹2,000 | Clean, functional finishes: laminate workstations, vinyl or basic carpet tile, painted gypsum ceiling, standard lighting |
| Medium | ₹2,400 | The usual corporate standard: better laminates, branded carpet tile, mixed gypsum and modular ceiling, task lighting |
| Good | ₹2,900 | Premium and executive: veneer or engineered-wood accents, premium carpet tile, glazed cabins, better meeting-room AV |
| High end | ₹5,000 | Flagship HQ: stone or marble in key areas, imported finishes, bespoke joinery, statement lighting |
ORR and Whitefield tech park rents run at a premium, but base infrastructure is typically strong, which can offset some of that with lower MEP upgrade costs compared to an older CBD building.
Bangalore runs about 10% above Delhi NCR: the city-by-city fit-out cost comparison sets the four cities side by side.
Worked budgets by office size
Indicative total project cost by floor size and finish tier, before GST, furniture included.
| Floor size | Basic | Medium | Good | High end |
|---|---|---|---|---|
| 2,000 sq ft | ₹40 lakh | ₹48 lakh | ₹58 lakh | ₹1 crore |
| 3,000 sq ft | ₹60 lakh | ₹72 lakh | ₹87 lakh | ₹1.5 crore |
| 5,000 sq ft | ₹1 crore | ₹1.2 crore | ₹1.45 crore | ₹2.5 crore |
| 10,000 sq ft | ₹2 crore | ₹2.4 crore | ₹2.9 crore | ₹5 crore |
| 25,000 sq ft | ₹5 crore | ₹6 crore | ₹7.25 crore | ₹12.5 crore |
Figures are indicative, based on our published rate card. Actual cost depends on your building condition, scope and site-specific factors.
Office fit-out cost per seat in Bangalore
Most Bangalore offices are planned at 80 to 100 sq ft per seat, counting workstations, cabins, meeting rooms, pantry and circulation. At that density, our rate card works out as below, before GST, furniture included.
| Tier | Rate per sq ft | Cost per seat (80 to 100 sq ft) |
|---|---|---|
| Basic | ₹2,000 | ₹1.6 to ₹2.0 lakh |
| Medium | ₹2,400 | ₹1.9 to ₹2.4 lakh |
| Good | ₹2,900 | ₹2.3 to ₹2.9 lakh |
| High end | ₹5,000 | ₹4.0 to ₹5.0 lakh |
A denser layout lowers the cost per seat; more cabins and meeting rooms raise it. To see how many seats fit your carpet area, try the office layout planner.
Where the money goes: a 10,000 sq ft example at Medium tier
A 10,000 sq ft office at our Medium (₹2,400 per sq ft) tier comes to ₹2.4 crore before GST. Here is the typical trade-by-trade split, based on standard fit-out cost proportions.
| Trade | Typical share | Approx. cost |
|---|---|---|
| Civil work and partitions | 22% | ₹52.8 lakh |
| False ceiling and lighting | 11% | ₹26.4 lakh |
| Flooring | 10% | ₹24 lakh |
| MEP: electrical, HVAC, fire, plumbing | 28% | ₹67.2 lakh |
| Furniture and workstations | 20% | ₹48 lakh |
| IT/AV and low-voltage cabling | 6% | ₹14.4 lakh |
| Design and project management | 3% | ₹7.2 lakh |
Splits are typical proportions for a corporate fit-out and vary by project. A real quotation itemises each trade against your actual scope.
Cost by area: Bangalore office markets at a glance
The rate card is the same across the city. What changes from one market to the next is the building stock, and that decides where your project lands within a tier.
| Market | Typical building stock | Common occupiers | Cost notes |
|---|---|---|---|
| Outer Ring Road (Bellandur to Marathahalli) | Large multi-tenant tech park campuses | Global capability centres, multinationals | Strong base services; landlord fit-out manuals, deposits and night work for noisy jobs |
| Whitefield | ITPB and township-style tech parks | IT and IT-enabled firms, multinationals | Warm shell floors are common, so MEP spend goes on extending systems |
| Manyata and Hebbal | Campus-style parks with centralised services | Technology and product companies | Strict contractor, permit and working-hour rules; large floor plates |
| Electronic City | Large IT campuses on Hosur Road | Delivery and back-office teams | Generous floor plates spread fixed costs; repeatable layouts keep cost down |
| MG Road and Residency Road | Older, smaller CBD buildings | Consulting, legal, banking, regional sales | May need new air conditioning, a panel upgrade or extra BESCOM load |
| Koramangala and Indiranagar | Independent and converted commercial buildings | Startups, design, media and consulting teams | Smaller floors carry fixed costs over less area; split or VRF air conditioning |
| Sarjapur Road | Grade A buildings near the ORR | Technology and product companies | Drawing review, deposits and night deliveries, as on the ORR |
What drives fit-out cost in Bangalore
Where a project lands within a tier depends on the building and the logistics. These are the points we check on a site visit.
Tech park warm shell or older bare floor
A warm shell floor in an Outer Ring Road, Whitefield or Manyata tech park usually comes with chilled water or air handling provisions, sprinklers and a power allocation, so the MEP budget goes on extending systems. An older CBD or Koramangala building may need new air conditioning, a panel upgrade or extra BESCOM load, which pushes the MEP share up.
Landlord charges and approvals
Many parks ask for a refundable fit-out deposit, contractor insurance and a formal drawing review, and some charge for after-hours lift use, security or utilities during the works. These are small next to the build cost but belong in the budget from day one.
Night work and delivery windows
Noisy work restricted to nights and weekends, booked service-lift slots and daytime limits on heavy vehicles all add labour hours. A quote that assumes unrestricted daytime working will under-price a Bangalore tech park job.
Monsoon and material choices
Bangalore's mild temperatures mean cooling is rarely the cost driver. The long monsoon season matters more: it calls for covered storage on site and care with moisture-sensitive materials such as MDF, veneer and carpet until the space is sealed and air-conditioned.
Local sourcing
Modular furniture, gypsum, glazing and standard MEP items are readily available from Bangalore suppliers, which keeps lead times and freight low. Imported finishes, natural stone and curved glass take longer and cost more to install.
Floor plate size
Large tech park floors spread fixed costs such as site setup, supervision and design over more square feet. Smaller CBD and startup-district floors carry the same fixed costs over less area, so they often land higher within a tier.
What the rate does not include
Our per sq ft rate covers civil work, MEP, finishes and furniture. Budget separately for:
- GST, charged on top of every rate on this page;
- landlord charges such as refundable fit-out deposits, contractor insurance and drawing review fees;
- after-hours building charges for lift use, security or utilities during the works;
- finishes above your tier, such as imported finishes, natural stone or curved glass beyond what the tier includes.
How long an office fit-out takes in Bangalore
Most office fit-outs take 6 to 16 weeks from design freeze to handover, depending on floor size, finish tier and whether the floor is warm shell or bare shell. Design and building approvals come before that, so start them as soon as the lease is close to signing.
- Our 28,000 sq ft Bangalore office with stone cladding and curved glass took 105 days against the 90 quoted, and the page explains what caused the delay.
To plan your own dates against a rent-free period, use the fit-out timeline calculator or read how long a fit-out takes and how much rent-free time to ask for.
Our work in Bangalore
A 28,000 sq ft office in Bangalore (about 18,000 sq ft carpet area), built around wall-clad natural stone, Italian marble at reception and clear and brown-tinted glass partitions, some of them curved. It was quoted at 90 days and handed over in 105, with the extra time coming from approvals on the client's side rather than design or construction. Read the project.
Planning a move or a refresh? Book a complimentary audit of your floor plan through the enquiry form, and we check it against your headcount before you sign.